Quick answer
Foreigners can buy off plan property in Brazil with a CPF number, on the same terms as Brazilians. Your protection rests on three things: the developer's incorporation record on the land's registry record, the segregated assets regime that ring-fences the project's money, and a contract that follows Law 13.786/2018 on delays and cancellation. A contract review checks all three before you sign or pay the first instalment.
How off plan buying works in Brazil, and where the risk sits
In Brazil, a developer may only sell units in a building that does not exist yet after registering the project at the registry office. The buyer pays instalments during construction and receives a registered title only after completion.
That gap, often two to four years, is where the risk lives: delays, price adjustments, changes to the project and, in the worst case, a developer that stops building. Three documents tell you how exposed you are.
Incorporation record: the licence to sell
The developer registers a file called the memorial de incorporação on the registry record of the land. Without that entry, selling units is irregular from the start.
Segregated assets: the project's money kept apart
When the patrimônio de afetação is noted on the record, the land and the buyers' payments for that project are separated from the developer's other debts.
Summary table: the contract on one page
Since Law 13.786/2018, every contract opens with a summary of price, instalments, price index, delivery date and what happens if you cancel. It is the first page to read.
When to have an off plan contract reviewed
Ideally as soon as the developer sends the contract, before any reservation fee. These six situations make the review more urgent for a buyer abroad.
- You are asked to sign at the launch. Launch events and sales stands are where buyers read the summary table least.
- The contract only exists in Portuguese. A brochure in English is not the contract. The signed Portuguese text is what binds you.
- Delivery is more than three years away. The longer the build, the more the price index, delays and project changes weigh.
- You pay in instalments from abroad. Each transfer needs a foreign exchange contract and a clear receipt from the developer.
- You plan to resell before the keys. Assigning the contract usually needs the developer's consent and a transfer fee.
- The developer is small or new to Bahia. A famous name protects nobody; a registered project with segregated assets does.
How the off plan contract review works
Five steps: the registry office first, then the developer, then the contract. The order matters, because a well-written contract cannot fix a project that was never registered.
The time frame depends on the length of the contract and on how quickly the developer answers requests for changes. Yours comes in the written proposal.
Buying a finished home instead? See the lawyer for buying property in Brazil
Step 1: Check the incorporation record
The land's registry record with the project registered, and the number and registry office quoted in the contract.
Step 2: Check segregated assets and the developer
The segregated assets entry, any bank mortgage on the land and certificates on the developer company.
Step 3: Read the contract and the summary table
Delivery date and grace period, price index, interest after the keys, penalties and cancellation rules.
Step 4: Ask for changes and map the remaining risk
What can be negotiated with the developer and, where nothing changes, exactly what risk you accept.
Step 5: Plan the keys, the deed and registration
What to check at handover, the occupancy permit (habite-se) and the unit's own registry record.
What the off plan contract review includes
The land's record, the developer and the contract. What depends on engineering or on a court case is not included, and is listed below.
Included in the review
Land registry record
Incorporation record and any charges on the land.
Segregated assets
The entry checked and what it covers in practice.
Developer certificates
Lawsuits, protests and debts of the company.
Contract and summary
Dates, grace period, index, penalties and cancellation.
Requested changes
The clauses worth asking the developer to amend.
Risk meeting
An online explanation of what stays in the contract.
Not included
- Technical inspection of the building. Construction quality and defects are assessed by an engineer.
- Price and return on investment. The review is legal, not a market appraisal.
- A lawsuit against the developer for delay. Court work is hired separately.
- An English version of the contract. It depends on confirmation of the service language.
What an off plan contract review costs
The fee comes in a written proposal after Dr. Gabriela sees the contract and the project. Brazilian Bar rules (Provimento 205/2021) do not allow lawyers to publish fees, so these are the factors that change the price.
| Factor | How it changes the work | Example |
|---|---|---|
| Length of the contract | Long contracts with annexes and building rules take longer to read | A contract with a 40-page specification |
| Number of units | Each unit has its own contract and payment plan | Two flats in the same tower to rent out |
| Negotiation | Asking the developer for changes adds rounds of discussion | Grace period and delay penalty renegotiated |
| Language | Explanations or a version in another language | A buyer living in the United Kingdom |
Purchase costs that are not legal fees
At handover you still pay the property transfer tax (ITIV, 3% in Salvador) and the deed and registration of the unit under the 2026 Bahia court fee table. The contract may also pass on the agent's commission, an assignment fee and the cost of opening the unit's own registry record: all of them must appear in the summary table.
Off plan property in Brazil in practice: the law in numbers, documents and mistakes
Law 13.786/2018 put numbers on delays and cancellations. Knowing them before you sign is what lets you compare the developer's contract with the law.
What Brazilian law gives an off plan buyer, and what to check
Six rules from the Incorporation Law, as amended by Law 13.786/2018, that every off plan contract must respect.
| Topic | What the law says | What to check in the contract |
|---|---|---|
| Grace period | Up to 180 days of delay without penalty, if written in the contract | A clear delivery date and grace period |
| Delay beyond the grace period | Cancel with a full refund plus a penalty, or keep the unit and receive 1% a month of what you paid | That the contract penalty is not lower than the law's |
| Buyer cancels | The developer may keep up to 25% of what you paid, or up to 50% with segregated assets | The percentage chosen and the refund date |
| Cooling-off period | 7 days to withdraw from a contract signed at a sales stand or away from the developer's office | Where the contract is signed |
| Summary table | Price, instalments, index, commission, dates and cancellation effects up front | That every figure matches the body of the contract |
| Agent's commission | May be charged to the buyer if shown separately | An amount separate from the unit's price |
Source: Law 4.591/1964, arts. 35-A, 43-A and 67-A, added by Law 13.786/2018. The clauses common to every purchase are explained in the guide to the preliminary contract.
Off plan or finished: where the risk sits in each purchase
An off plan purchase trades a lower entry price and a payment plan for construction risk. The table shows where each risk lives.
| Point | Off plan | Finished property |
|---|---|---|
| What is checked | Incorporation record, segregated assets and developer | The unit's registry record and the seller |
| Main risk | Delay or a stalled building site | The seller's debts or charges on the unit |
| Price | Instalments adjusted by an index during the build | Fixed when you sign |
| Your own registry record | Only after the occupancy permit and the unit records are opened | Already exists and can be read |
| Money from abroad | Many transfers over years, each with its exchange contract | Usually one or two transfers |
In Brazil the deed alone does not make you the owner; that is why registration matters as much at handover as on the day you sign.
Documents to ask the developer for before you sign
An organised developer sends these eight items without delay. Anything it cannot send is already an answer.
- Up-to-date registry record of the land
- Number and date of the incorporation record
- Segregated assets entry on the record
- The full contract with its summary table
- Specification and floor plan of the unit
- Construction schedule and delivery date
- Building permit from the town hall
- Certificates on the developer company
Get the Brazil CPF number the contract will ask for
Common mistakes foreign buyers make off plan
These four mistakes surface when the buyer wants to cancel or claim for a delay, when it is already late.
- Trusting the brochure, not the record. A brochure is never registered. Instead: ask for the land's record with the incorporation entry.
- Ignoring the price index. Instalments adjusted for years change the final price in reais. Instead: simulate the balance with the contract's index.
- Counting the date without the grace period. Delivery may come 180 days late with no penalty. Instead: plan your move or rental with that margin.
- Taking the keys and forgetting registration. Without a registered deed, the unit stays in the developer's name. Instead: set a deadline for the deed in the contract.
The laws behind an off plan purchase in Brazil
Three laws explain the developer's duties, the protection of the project's money and the numbers on delay and cancellation.
- Law 4.591/1964: the Incorporation Law. Requires the developer to register the project before selling units and sets the developer's duties to buyers. Law 4.591/1964 on the Planalto website
- Law 10.931/2004: segregated assets. Created the patrimônio de afetação, which keeps each project's land and money apart from the developer's other business. Law 10.931/2004 on the Planalto website
- Law 13.786/2018: delays and cancellation. Added the summary table, the 180-day grace period, the delay penalties and the limits on what a developer may keep. Law 13.786/2018 on the Planalto website The numbers in the law are a floor. A contract below them can be challenged, but it is far simpler to fix it before you sign.
Why choose Gabriela Pereira Advocacia to review the off plan contract
Because an off plan buyer's protection is at the registry office before it is in the contract. Dr. Gabriela Pereira worked on the registry side and knows how to read an incorporation record.
- A registrar's reading of the project. Registry officer in Bahia from 2017 to 2023, in Public Records and Property Registration.
- The developer checked, not only the contract. Segregated assets, bank charges on the land and company certificates come before the clauses.
- The law's numbers side by side. Grace period, penalty and retention in your contract compared with Law 13.786/2018.
- A review for buyers far away. Contract by email and online meetings for buyers in another state or another country.
- Real estate law specialist (UNIFACS). Former lecturer in Real Estate Law at FTC, at undergraduate and graduate level.
- Credentials you can verify. OAB/BA 30.943 in the national lawyers' register and a 5.0 rating on Google.
Questions about off plan property in Brazil
What buyers ask when the developer's contract arrives, or after signing, when they want to know their rights.
Can foreigners buy off plan property in Brazil?
Yes. An apartment or house in a development has no special limit for foreigners. You need a CPF number, and the money should come in through an official foreign exchange contract.
Can a large developer's contract be changed?
Not always. But you can know the exact risk before signing and, on several points, ask for changes or an addendum. Deciding with that information already changes the purchase.
How do I know the project is registered?
From an up-to-date registry record of the land, requested from the registry office. The incorporation record appears as its own entry, with a number and a date.
How late can the developer deliver?
Up to 180 days after the promised date without penalty, when that grace period is in the contract. After that, you may cancel or claim compensation for the delay.
If I cancel, how much do I get back?
It depends on the contract and on segregated assets: the developer may keep up to 25% of what you paid, or up to 50% if the project has segregated assets, plus the agent's commission.
Can I sign the contract from abroad?
Yes, with an electronic signature or through an attorney in Brazil. The review itself is done with digital documents and online meetings. Explanations in English depend on confirmation.
When does the unit become mine on the registry record?
After completion, when the occupancy permit is issued, the unit gets its own registry record and your deed is registered on it. Until then, you hold contractual rights.
How is the fee for the review set?
Through a written proposal, after Dr. Gabriela sees the contract and the project. Brazilian Bar rules do not allow fees to be published on the website.
Read before you sign with the developer
The content of this website is for information only and does not replace a lawyer’s review of your case.